Enecor

Pampa holds a 70% interest in Enecor, an independent power transmission company, under a 95-year concession valid until 2088. Enecor subcontracts Transener for the operation and maintenance of the 21 km 132 kV double-circuit lines from the Paso de la Patria transforming station in the Province of Corrientes.

On October 3, 2024, the SE initiated the RQT for independent transporters (Resolution No. 706/24), later postponing the process until July 9, 2025 (ENRE Note No. 128974332). However, on January 7, 2025, the procedure was resumed, and the ENRE modified the approval terms for the values to be remunerated during the following tariff period (Resolution No. 5/25). The corresponding information was submitted by January 20, 2025, and as of the closing date, no further news was reported.