Parque Pilar Thermal Power Plant (‘CTPP’)

To the north of Greater Buenos Aires, in the Industrial Complex of the district of Pilar, CTPP has a 100 MW capacity, 0.2% of the country’s installed capacity, through 6 Wärtsilä motor generators with a 43% efficiency. CTPP may indistinctly consume FO stored in its own tanks or natural gas, supplied through a dedicated gas pipeline connected with TGN’s main gas pipeline. From 2018 to 2024, its historical average annual generation was 234 GWh, with a generation record high of 321 GWh in 2022 and a record low of 168 GWh in 2019.

*Only available in spanish

 

The following chart shows certain relevant statistical data on CTPP:

2023 2024
Net Generation (GWh) 274 192
Purchases of Energy (GWh)
Total Energy Sales (GWh) 274 192
Average Price (US$/MWh) 135 na
Average Gross Profit (US$/MWh) 107 na

Note: Gross Margin before depreciation and amortization.

 

Technical Data

Unit Installed Capacity (MW) Efficiency Fuel Start-Up Type of Unit Remuneration
PILBDI01~06 100 45% Natural gas or fuel oil 2017 6 motor generators PPA 21/16