In October 2024, with an approximate US$250 million investment, we completed the installation of all the wind turbines and civil works at PEPE 6, commissioned in November 2024. PEPE 6 has 31 Vestas wind turbines of 4.5 MW each and a total installed capacity of 139.5 MW, representing 0.3% of Argentina’s installed capacity. In 2024, it generated 197 GWh.
*Only available in spanish
The following chart shows certain relevant statistical data on PEPE VI:
2023 | 2024 | |
---|---|---|
Net Generation (GWh) | – | 197 |
Purchases of Energy (GWh) | – | – |
Total Energy Sales (GWh) | – | 195 |
Average Price (US$/MWh) | – | 64 |
Average Gross Profit (US$/MWh) | – | 59 |
Note: Gross Margin before depreciation and amortization.
Technical Data
Unit | Installed Capacity (MW) | Start-Up | Type of Unit | Remuneration |
---|---|---|---|---|
PEP6EO | 140 | November 2024 | 31 wind generators | MAT ER |